No More Delays In Lcs Project Despite Removing Two Contractors Bns


 


There will be no delays in the construction of littoral combat ships (LCS) although two contractors appointed by Boustead Naval Shipyard Sdn Bhd (BNS) have had their contracts terminated. 
This is the assurance given by BNS, the main contractor behind the LCS project following the termination of Contraves Advanced Devices Sdn Bhd (CAD) and Contraves Electrodynamics Sdn Bhd (CED).
Both companies, which were previously entrusted to purchase equipment from original equipment manufacturers (OEMs) to build the vessels, recently had their letters of award (LOAs) voided amid allegations surrounding the LCS scandal.
"We do not foresee the termination of CAD and CED will delay the project.
"BNS is committed to delivering the vessels in accordance with the new schedule, which is to be negotiated with the government," BNS chief executive officer Azhar Jumaat was quoted as saying by The Edge.
"The termination will allow BNS to negotiate directly with the relevant OEMs and this can be done within the proposed delivery period for the vessels," he said.
Azhar, however, said the OEMs in the current contract will remain involved in the project, as BNS is only terminating the intermediaries.
"The contract termination only refers to removing intermediaries. We are not replacing OEMs appointed through CAD and CED. Thus, there is no issue with the nomination of new contractors.
“And there is no additional cost to the government (to complete the vessels) due to the termination of CAD and CED," Azhar said.
Senior Defence Minister Hishammuddin HusseinOn Aug 8, Senior Defence Minister Hishammuddin Hussein said he expected the first of six vessels to be delivered in two years’ time, despite an initial target date in 2019.
He said the first vessel will not involve new allocations from the government.
The Sembrong MP added that "additional allocations" for the LCS project will only be considered after the first of the six ships is delivered.
A media tour of the LCS shipyard in early last month revealed that five of the six ships are under construction, with the first ship being only 60 percent complete as of April.
A Public Accounts Committee report (PAC) on the project revealed a huge cost overrun amounting to RM1.4 billion in the RM9 billion contract, with RM6 billion paid as of 2020.
As for the remaining vessels’ completion, Azhar previously said that LCS2 was 48 percent complete, followed by LCS3 (43 percent), LCS4 (36 percent), LCS5 (22 percent), while construction for LCS6 has not begun. - Mkini


Artikel ini hanyalah simpanan cache dari url asal penulis yang berkebarangkalian sudah terlalu lama atau sudah dibuang :

http://malaysiansmustknowthetruth.blogspot.com/2022/09/no-more-delays-in-lcs-project-despite.html

Kempen Promosi dan Iklan
Kami memerlukan jasa baik anda untuk menyokong kempen pengiklanan dalam website kami. Serba sedikit anda telah membantu kami untuk mengekalkan servis percuma aggregating ini kepada semua.

Anda juga boleh memberikan sumbangan anda kepada kami dengan menghubungi kami di sini
Pssc Urged To Quiz Macc On Delays In Lcs Probe

Pssc Urged To Quiz Macc On Delays In Lcs Probe

papar berkaitan - pada 9/9/2022 - jumlah : 205 hits
The Parliament s Special Select Committee on agencies under the Prime Minister s Department has been urged to investigate the anti graft agency MACC Veteran MP Lim Kit Siang said this was necessary due to the lack of progress in the MACC s ...
State Minister Solar Project In Sarawak Must Continue Despite Rosmah S Conviction

State Minister Solar Project In Sarawak Must Continue Despite Rosmah S Conviction

papar berkaitan - pada 2/9/2022 - jumlah : 142 hits
The RM1 25 billion solar hybrid energy project for 369 rural schools in Sarawak must be continued said State Tourism Creative Industry and Performing Arts Minister Abdul Karim Rahman Hamzah This is despite Rosmah Mansor the wife of former p...
Focus On The Issue Of Missing Money From Lcs Project Says Rafizi

Focus On The Issue Of Missing Money From Lcs Project Says Rafizi

papar berkaitan - pada 4/9/2022 - jumlah : 177 hits
The issue that needs to be addressed is the money that allegedly went missing from the littoral combat ship project says Rafizi Ramli The findings of the forensic audit are not hearsay and it is not my document It is a government document t...
More Time Needed For Lcs Probe Says Macc Chief

More Time Needed For Lcs Probe Says Macc Chief

papar berkaitan - pada 8/9/2022 - jumlah : 187 hits
The Malaysian Anti Corruption Commission needs more time for its investigation into the troubled RM9 billion littoral combat ship project says top graft buster Azam Baki The MACC chief commissioner told a press conference the anti graft age...
Rafizi Why Did Zainab S Alizes Marine Buy Mineral Water Cotton Buds As Part Of Lcs Project S Spare Parts

Rafizi Why Did Zainab S Alizes Marine Buy Mineral Water Cotton Buds As Part Of Lcs Project S Spare Parts

papar berkaitan - pada 26/8/2022 - jumlah : 173 hits
PKR deputy president Rafizi Ramli today claimed that Alizes Marine the company owned by Zainab Mohd Salleh the alleged wife of Minister in the Prime Minister s Department Datuk Abdul Latiff Ahmad made purchases that did not meet the require...
Diamonds Aren T Forever Two Down Few More To Go

Diamonds Aren T Forever Two Down Few More To Go

papar berkaitan - pada 2/9/2022 - jumlah : 169 hits
Rosmah Mansor the wife of former prime minister Najib Abdul Razak was convicted over three graft charges linked to the RM1 25 billion solar hybrid project The Kuala Lumpur High Court this afternoon sentenced Rosmah Mansor to 10 years in jai...
Rafizi Berapa Banyak Dari Peruntukan Rm1 7b Lcs Diguna Beli Putik Kapas

Rafizi Berapa Banyak Dari Peruntukan Rm1 7b Lcs Diguna Beli Putik Kapas

papar berkaitan - pada 26/8/2022 - jumlah : 262 hits
malaysiakini comDiterbitkan Aug 25 2022 3 57 PMDalam serangan terbarunya berkaitan skandal kapal tempur pesisir Timbalan Presiden PKR Rafizi Ramli mempersoalkan sebanyak mana wang daripada peruntukan RM1 7 bilion untuk alat gantian kapal it...
Sebahagian Laporan Audit Forensik Kapal Lcs Dihitamkan Kerajaan Perlu Beri Penjelasan Fahmi

Sebahagian Laporan Audit Forensik Kapal Lcs Dihitamkan Kerajaan Perlu Beri Penjelasan Fahmi

papar berkaitan - pada 25/8/2022 - jumlah : 119 hits
Kerajaan Malaysia yang menyahklasifikasikan laporan audit forensik pembinaan kapal tempur pesisir sejak kelmarin perlu memberi penjelasan mengapakah bahagian bahagian tertentu muka surat laporan itu dihitamkan Menurut Ahli Parlimen Lembah P...
Fuhhhh Project Gini Pun Ada

Fuhhhh Project Gini Pun Ada

papar berkaitan - pada 12/9/2022 - jumlah : 108 hits
MOHD MUKHLIS MOHD SYARIFFKalau BN masih lagi berkuasa jangan kata 1MDB sapu bawah karpet anda juga masih membayar 250 untuk 20megabit Streamyx Ini nama dia ada political will yang sekarang ini auto pilot cukup bulan ambil elaun jihad
Johor Apa Yang Menarik Di Iskandar Puteri

Business Marketing For Success

Ayam Madu Sira Masak Guna Resipi Ni Memang Sangat Sedap

Andika Putera Biodata Usahawan Kacak Geng Old Money

Ikan Siakap Masak Berlada

Biarkan Aku Menangis

Apa Itu Old Money Memahami Konsep Old Money Dan Keistimewaannya Yang Unik

Lirik Lagu Nombor 1 Sleeq


echo '';
Senarai Lagu Separuh Akhir Muzik Muzik 39 Semi Final Muzik Muzik SFMM 2024 Persaingan Merebut Tiket Ke AJL Anugerah Juara Lagu

Biodata Terkini Fairuz Selamat Q Face Peserta Gegar Vaganza 2024 Musim 11 GV11 Penyanyi Lagu Izinkanlah

Biodata Terkini Arrora Salwa Salwa Razak Peserta Gegar Vaganza 2024 Musim 11 GV11 Penyanyi Lagu Ahmad

Biodata Terkini Penyanyi Liza Aziz Peserta Gegar Vaganza 2024 Musim 11 GV11 Adik Beradik Kepada Azlina Aziz

Senarai Peserta Gegar Vaganza 2024 Musim 11 GV11 Tonton Konsert Minggu 1 Pada 24 November Live Di Astro Ria Sooka Online


Breakfast Hari Ini

Lirik Lagu Sejarah Dato Sri Siti Nurhaliza

Latheefa Koya Tak Nak Masuk Umno Ker

Wings Mayang Sulit Chord

Siti Nurhaliza Sejarah Chord

Fakta Tentang Susu Kucing Dan Jenama Susu Untuk Dicuba