Littoral Combat Ships Fiasco A Litany Of Sleaze
From Kua Kia Soong
The Malaysian Anti-Corruption Commission (MACC) detained two chief executive officers on Jan 24 in its investigation into the procurement of six littoral combat ships (LCS) to be built by Boustead Naval Shipyard Sdn Bhd (BNS).
Both were suspected of committing malpractice and receiving bribes through payments to three companies abroad.
One of them is also suspected of receiving bribes from a sub-contractor appointed to handle the project.
The next day, the MACC arrested a 62-year-old broker who is suspected of having engineered ghost projects to siphon off a total of RM24 million.
The man allegedly worked with a former CEO of a company involved in the procurement of the ships. Is this a surprising revelation?
In 2019, the defence ministry announced that the Cabinet had decided that the Boustead Group could resume the stalled construction of the six LCS.
These ships are small, fast warships designed for shallow coastal waters.
The failure of the contractor to complete the detailed design by the deadline, and a delay in finalising the acquisition of a large portion of the equipment under its responsibility, were among the causes of the delay in delivering the six littoral combat ships to the Royal Malaysian Navy (RMN).
Then defence minister Mohamad Sabu described the work as being of unsatisfactory quality and that it had mismatched the customised specifications, resulting in delays to the April 2019 delivery date.
Mohamad said the ministry, however, did not stop the purchase as it had already paid RM6 billion.
The project, worth RM9.128 billion, was awarded to BNS by the government through the defence ministry.
In August 2020, as he answered questions in Parliament about the non-delivery of ships, the then defence minister Ismail Sabri Yaakob said the ministry was considering terminating the contract with BNS, among other options.
He noted that doing so would have adverse effects on the Armed Forces Fund Board (LTAT), the military pension fund which owns 59.4% of Boustead Holdings.
Such a move would affect soldiers who are contributors, should the project be halted.
“For the record, Boustead Naval Shipyard Group is a government-linked company, managed by mostly Malay Bumiputeras,” he said.
This is yet another example of a failed “Bumiputeras Only” policy and vested interests that afflict the whole military industrial complex in Malaysia.
Sorry, but I warned the nation in 2011
On Feb 12, 2011, I wrote the article, “6 Patrol Vessels: Watch how the Cost Inflates”, which was published in several online news outlets.
At the time, some defence analysts and a retired admiral had come out in support of the government’s purchase of six New Generation Patrol Vessels (NGPVs), arguing that these were sophisticated ships and weaponry and thus the price was reasonable.
They also tried to justify the closed-door negotiations by saying it’s the arms companies that do not want their proposals and offer prices to be made available to their competitors. How often have we heard that?
This is the standard explanation we have been fed all these years to justify the outrageous figures in our military budget compared, for example, with the budget for health and other urgent social services.
This attempt at mystifying defence contracts has gone on long enough under the technical pretext that it is “rocket science” that taxpayers and MPs apparently cannot hope to comprehend.
Using the convenient excuse of “national security”, the defence ministry keeps in shroud the specifications for these sophisticated equipment and weapons systems they are supposed to be fitted with.
The record of the navy’s procurements
The naval dockyard at Lumut had been completed in 1984 at a cost of RM650 million but it had not been fully used.
In 1989, the auditor-general pointed out that the navy had, because of staff shortage, sent many ships to private dockyards for servicing,
“Only 21 of the 36 ships scheduled for overhauling in 1986 were serviced in that year and in 1987 only 15 out of 43 ships were overhauled.
“As a result, the ships were serviced by private dockyards at a cost of RM10.28 million in 1985, RM7.60 million in 1986 and RM10.98 million in 1987.” (The Star, Dec 16, 1989)
The auditor-general found that some of the facilities had never been used, resulting in the deterioration of some equipment.
He also found that the navy had not complied with regulations when it made bulk purchases of spare parts for its Central Logistics Depot – spare parts and stores valued at RM13.4 million for 1986 and RM4 million for 1987, which had been bought through local orders and quotations when they should have been acquired through a contract after a public tender.
In 1991, because of the RM5 billion arms deal signed by our maverick prime minister Dr Mahathir Mohamad and the Iron Maiden Margaret Thatcher, the defence ministry announced a contract to purchase two corvettes from Yarrow shipbuilders, in the UK, costing RM2.2 billion (New Straits Times, Nov 11, 1991).
The RM2.2 billion for just two corvettes was RM1 billion more than what had been allocated to the science, technology and environment ministry at the time, for capital expenditure under the Sixth Malaysia Plan.
Two weeks later, then defence minister Najib Razak was quoted as saying the navy required 16 offshore patrol vessels (OPVs).
But due to financial constraints, the navy could only afford four or five of these locally built OPVs. The ministry of defence had budgeted RM85 million per OPV, excluding guns (NST, Nov 25, 1991).
Mahathir and his defence minister might have done well to ask themselves the wisdom of buying two corvettes for RM2.2 billion or using that budget to buy more than 20 OPVs at RM85 million-a-piece from Penang Shipbuilding and Construction – Naval Dockyard Sdn Bhd (PSC).
In my 2010 article entitled “Questioning Arms Spending in Malaysia: From Altantuya to Zikorsky”, I discussed the emergence and growth of our domestic Military Industrial Complex and how this has led to the continuance of non-transparency in the way contracts are given out and how taxpayers are subsidising these rather privileged “appointed” local Bumiputera contractors.
By mid-2006, only two barely operational patrol boats had been delivered.
In 2007, the auditor-general tabled a report in Parliament alleging that the contract was in serious trouble.
There were 298 recorded complaints on the two boats, which were also found to have 100 uncompleted items in one boat and 383 in the other.
According to the auditor-general, progressive payments amounting to RM943 million had been paid out even though he could find no payment vouchers or relevant documents dealing with the payments.
He attributed the failure to serious financial mismanagement and technical incompetence, stemming from the fact that PSC had never built anything but trawlers or police boats before being given the contract by the defence ministry (Auditor-General’s Report 2006, Sept 7, 2007)
The Auditor-General Report estimated that the government could claim at least RM214 million in penalties for the late delivery of the two OPVs and non-delivery of the remaining four.
However, the Cabinet decided to waive the claim of penalties and even awarded the contractor an increase in the contract price of RM1.4 billion in January 2007.
The defence ministry paid in advance RM4.26 billion to the contractor in December 2006 when the progress of the work done only amounted to RM2.87 billion.
Despite the fiasco and the great financial loss to taxpayers, the mammoth contract was awarded to yet another local company – Boustead Holdings, which effectively took control.
Transparency in arms procurements
In 2012, Transparency International (TI) found that two-thirds of parliaments and legislatures around the world failed to exercise sufficient control over their defence ministry and the armed forces, and 70% of the largest arms importers left the door open to corruption.
Malaysia had a score of 25.14 out of 100% in a six-band rank which ranked “Very High” risk of corruption among 21 other countries.
In this report, TI identified seven key areas in which parliaments may reduce corruption, namely (a) Budget Oversight & Debate; (b) Budget Transparency; (c) External Audit; (d) Policy Oversight & Debate; (e) Secret Budgets Oversight, (f) Intelligence Services Oversight; and (g) Procurement Oversight.
Parliamentarians should push for greater transparency in defence ministry arms procurements and seriously debate the defence budget and monitor the procurement process to prevent the repetition of such scandals. There should be special select committees to scrutinise any big budget procurements.
The Auditor-General’s Report 2019 pointed out that the defence ministry had not imposed liquidated damages against BNS.
This prompted the defence ministry to say, in its response to the report, that it had issued a notice to the shipbuilder in June 2020.
According to the report, the defence ministry demanded BNS to pay RM217.5 million in a notice dated June 15. As of June 30, 2020, the ministry had yet to issue a demand letter to the company requesting for liquidity damages. Instead, the ministry only issued a reminder notice to the company on June 14, 2019.
Malaysia resumes project despite ongoing corruption probe
In 2020, the government said it would allow BNS to resume construction of littoral combat ships for the country’s navy despite its failure to deliver on schedule and an unfinished probe into missing funds in the billion-ringgit project.
It was reported that the move will preserve 1,600 local jobs and more than 400 small and medium-sized businesses owned by Malay Bumiputeras, Ismail said in a statement, which did not say anything about the past delivery delays or corruption allegations.
At an August 2020 parliamentary debate, Ismail acknowledged that none of the LCS had been completed in over nine years, despite the government having paid RM6 billion so far.
There is no glory in predicting a tragedy affecting billions of taxpayers’ monies when the country is going through the Covid-19 crisis, and our national coffers are under even greater strain.
Still, the blame for the fiasco should be laid squarely on the politicians who did not adhere to the necessary SOPs regarding transparency in framing our defence priorities and transparency in arms procurements.
It is even more bewildering that such a multi-billion ringgit contract can go on with little or no supervision to ensure that public funds are prudently spent.
National interests or Boustead’s interests?
It is time to open our defence policy for public debate. The people need to be told who our perceived enemies are so that we can discuss the best means to combat these threats.
The government should be made to produce annual defence white papers and be open about all these defence procurements.
Our defence analysts know that the specifications for these vessels will ultimately be known anyway and the justification for secrecy in contract negotiations is unjustified.
Finally, it is unclear whether these fabulous defence equipment purchases are in the national interest or merely to fill the construction pockets of another vested interest, namely our local military industrial complex.
And as we look ahead to facing the climate crisis and food security as “Keluarga Malaysia”, the country should seriously consider the necessity for a military industrial complex, our “Bumiputeras Only” policy and arraign our production to socially useful products and not weapons of destruction and gross carbon emitters. - FMT
Kua Kia Soong is a former MP and an FMT reader.
The views expressed are those of the writer and do not necessarily reflect those of MMKtT.
Artikel ini hanyalah simpanan cache dari url asal penulis yang berkebarangkalian sudah terlalu lama atau sudah dibuang :
http://malaysiansmustknowthetruth.blogspot.com/2022/01/littoral-combat-ships-fiasco-litany-of.html