Boustead Refutes Obsolete Equipment Claims During Media Visit To Lcs Shipyard


 



Equipment stored in warehouses at the Boustead Naval Shipyard (BNS) is not obsolete but in the process of obsolescence, said the company’s chief executive officer Azhar Jumaat today.
The BNS chief said this in response to a Public Accounts Committee’s (PAC) report on littoral combat ships (LCS), claiming that about 15 percent of total inventory worth RM1.7 billion was obsolete.
During a media visit to the shipyard in Lumut, Perak today, Azhar told members of the press that these claims were inaccurate.
“A salient point highlighted in the PAC report is that 15 percent of the equipment system (stored at BNS) was obsolete. That’s not entirely accurate in terms of its description.
“…(It is) in the process of obsolescence, moving to the state of obsolete. Why is it being put into that situation is because some of the equipment is being stored for a long period of time which requires for periodical preservation,” he said, adding that the stored equipment can be utilised for a minimum of 25 years from now and is ready to be boarded onto the ships.
BNS CEO Azhar JumaatAzhar justified the need to order and store the equipment in advance to the long construction lead times, adding that it takes about 20 months for the ship’s main engine to be imported from Germany to Malaysia.
Among the equipment were electrical and mechanical equipment, which included the ship’s engines.
However, he assured BNS was in the process of engaging with various original equipment manufacturers (OEMs) to conduct a survey on the condition of the equipment, including additional costs that may incur.
During the visit, Azhar led reporters from various media outlets to visit the site’s storage facility, which contained BNS’ inventory, in an attempt to be transparent about the ship’s construction.
Reporters were also allowed to board and tour the first navy LCS (LCS1), which was at 60 percent of its completion stage as of April this year.
He told some reporters that LCS2 was at 48 percent completion stage, followed by 43 percent (LCS3), 36 percent (LCS4), and 22 percent (LCS5). Construction for LCS6 has not yet begun.
All five LCS ships are being built concurrently, Azhar added, as each ship takes an average of four years.
He said LCS1 would take about two more years to reach its completion stage.
RM6b being utilised
PAC’s report revealed a huge overrun in cost amounting to RM1.4 billion in the RM9 billion contract which was awarded to BNS in 2011.
BNS was awarded the job in 2011 through direct negotiation, and RM6 billion was paid as of 2020, but it missed the targeted delivery date of 2019.
According to the contract, BNS should have delivered the first ship in April 2019 and two ships in February and March 2020, respectively.
Despite missing the deadline in delivering the LCS, the cabinet in April 2021 agreed for Boustead Group to continue with the LCS project.
It is understood that BNS’ open doors to the media today were to clarify doubts in the procurement of the LCS ships.
Azhar maintained that the RM6 billion funds supplied to them were being fully utilised by BNS, despite its cash flow issues.
With RM 1.7 billion worth of equipment in storage, Azhar revealed that another RM1.8 billion’s worth had already been onboarded onto the ships.
However, Azhar refused to divulge where the balance of RM2.5 billion was spent.
“I am not going into that detail yet. For me to divulge that information about the RM1.8 billion (worth of equipment) that is already on board is enough for you to have a sense that about RM3.5 billion out of the RM6 billion was spent on actual real requirements.
“Of course, you must understand you have to pay for the overhead and the project management and to finance the costs for the insurance, electricity, infrastructure, construction and all that.
“The other RM2.5 billion go towards those activities and requirements. I am not going to be able to give the detailed background of those, but you should know that it is quite fair distribution in the cost breakdown,” he said.
Earlier, he had told the media that RM200 million was spent on infrastructure.
In 2019, the LCS project was halted due to BNS’ cash flow issues that resulted in non-payment to OEMs.
However, Azhar said today that construction was still carried out sans the OEMs.
“The work that could be done between us, within our means, we can continue because we can’t afford to stop completely,” he said.
He later added that there were ongoing sessions between BNS, the government and the OEMs to discuss the best way to move forward.
The cabinet, in April last year, agreed for Boustead Group to continue with the LCS project, which had been delayed since 2019, with conditions to be complied with by the company. - Mkini


Artikel ini hanyalah simpanan cache dari url asal penulis yang berkebarangkalian sudah terlalu lama atau sudah dibuang :

http://malaysiansmustknowthetruth.blogspot.com/2022/08/boustead-refutes-obsolete-equipment.html

Kempen Promosi dan Iklan
Kami memerlukan jasa baik anda untuk menyokong kempen pengiklanan dalam website kami. Serba sedikit anda telah membantu kami untuk mengekalkan servis percuma aggregating ini kepada semua.

Anda juga boleh memberikan sumbangan anda kepada kami dengan menghubungi kami di sini
Isu Lcs Hishammuddin Perlu Jelaskan Kemampuan Kewangan Boustead Naval Shipyard Chin Tong

Isu Lcs Hishammuddin Perlu Jelaskan Kemampuan Kewangan Boustead Naval Shipyard Chin Tong

papar berkaitan - pada 10/8/2022 - jumlah : 145 hits
Chin Tong mendakwa BNS pernah cuba meminta komitmen Kerajaan bernilai RM53 bilion untuk kerja MRO bagi tempoh 30 tahun akan datangKUALA LUMPUR Kerajaan perlu berterus terang sekiranya sekiranya kontraktor utama projek kapal tempur pesisir B...
The Pac S Lcs Site Visit Was Heart Breaking

The Pac S Lcs Site Visit Was Heart Breaking

papar berkaitan - pada 13/8/2022 - jumlah : 248 hits
MP SPEAKS Shortly after the Public Accounts Committee report on the procurement of littoral combat ships was tabled a reporter friend texted me asking How did you feel I replied Heart breaking We have conducted 10 proceedings including a si...
Lcs Subcontractors Overcharged Govt By Three Times Claims Rafizi

Lcs Subcontractors Overcharged Govt By Three Times Claims Rafizi

papar berkaitan - pada 10/8/2022 - jumlah : 153 hits
Putrajaya billed with RM1 185 billion but works only cost RM397 million says PKR deputy chief Two packages worth RM1 185 billion was awarded to subcontractor Contraves Advanced Devices Sdn Bhd by littoral combat ship provider Boustead Naval...
Skandal Lcs Apa Media Indonesia Kata Terhadap Malaysia Bacalah

Skandal Lcs Apa Media Indonesia Kata Terhadap Malaysia Bacalah

papar berkaitan - pada 17/8/2022 - jumlah : 308 hits
ZONAJAKARTA COM Indonesia dan Malaysia adalah dua negara yang sama sama pernah membuat kapal tempur pesisir Kapal tempur pesisir atau kapal tempur littoral adalah kapal yang memiliki ukuran relatif lebih kecil dan ditujukan untuk operasi di...
Rafizi Claims Najib S Associate Gave Away Control Of Lcs Subcontractor

Rafizi Claims Najib S Associate Gave Away Control Of Lcs Subcontractor

papar berkaitan - pada 12/8/2022 - jumlah : 172 hits
PKR deputy president Rafizi Ramli today claimed that an associate of former premier Najib Abdul Razak had effectively ceded the Armed Forces Pension Fund s control over the littoral combat ship project to a foreign company despite holding a...
Boustead Forensic Audit Report On Lcs To Be Declassified

Boustead Forensic Audit Report On Lcs To Be Declassified

papar berkaitan - pada 20/8/2022 - jumlah : 167 hits
Defence minister Hishammuddin Hussein ordered Boustead to declassify an audit report on the LCS project an Umno leader said PETALING JAYA Defence minister Hishammuddin Hussein has ordered Boustead Heavy Industries Corporation to declassify ...
Lcs Combat System May Be Obsolete In 10 Years Says Mp

Lcs Combat System May Be Obsolete In 10 Years Says Mp

papar berkaitan - pada 12/8/2022 - jumlah : 189 hits
An opposition MP has warned that the combat management system of the littoral combat ships currently under construction may be obsolete within the next decade after a change of specifications Citing the Public Accounts Committee s report on...
Pac Chief Chides Bns Ceo S Nonchalance On Obsolete Equipment

Pac Chief Chides Bns Ceo S Nonchalance On Obsolete Equipment

papar berkaitan - pada 15/8/2022 - jumlah : 185 hits
Boustead Naval Shipyard Sdn Bhd chief executive officer Azhar Jumaat has issued contradictory statements regarding obsolete equipment meant for the littoral combat ship project said Public Accounts Committee chief Wong Kah Woh Yesterday Azh...
Ltat Boss Boustead Forced To Use Lcs Money To Pay Off Bad Debts

Ltat Boss Boustead Forced To Use Lcs Money To Pay Off Bad Debts

papar berkaitan - pada 10/8/2022 - jumlah : 209 hits
Armed Forces Pension Fund chief executive officer Ahmad Nazim Abdul Rahman said Boustead Naval Shipyard Sdn Bhd was forced to use part of the funds meant for the littoral combat ships procurement to pay off the bad debts of another old proj...
Tremendous Nadi Collaboration

Kebaikan Rawatan Rendaman Kaki Bersama Garam Bukit Dan Ais Batu

Salam Dalam Salat Jenazah Sekali Atau Dua Kali

10 Praktik Keberlanjutan Yang Wajib Diterapkan Di Tahun 2025

Takwim Cuti Persekolahan Tahun 2025 2026

Whatsapp Tak Lagi Sokong Peranti Android Lama Mulai 1 Januari 2025

Melawat Ke Sand Dunes Di Tottori Jepun

10 Perusahaan Rental Mobil Pontianak Resmi Update 2025


echo '';
5 Insiden Jalan Sesak Yang Berlaku Lebih 24 Jam Durasinya

Senarai Lagu Tugasan Konsert Minggu 6 Gegar Vaganza 2024 Musim 11

Keputusan Markah Peserta Konsert Minggu 5 Gegar Vaganza 2024 Musim 11

10 Filem Drama Seram Melayu Berhantu Terbaru 2024 2025 Mesti Tonton

One In A Million 2024 Senarai Peserta Juri Format Pemarkahan Hadiah Dan Segala Info Saksikan Live Di TV3 Malaysia Dan Tonton Calpis Soda OIAM


Resepi Udang Khamped Padu Mudah Sedap Dan Confirm Licin Pinggan

The Skill Hexagon The Power Of Multifaceted Abilities

Skill Up Steam Curator

Dua Sahabat Makan Ikan Mentah Minum Air Laut Sepanjang Hanyut

Godox Perkenalkan Lampu Led Knowled Ms60r Bi Yang Sangat Fleksibel

Adi Putra Alami Jangkitan Kuman Di Paru Paru Kini Dalam Keadaan Baik