Pan Borneo Highway Is 82 Complete Says Works Minister


 
Federal works minister Fadillah Yusof taking in the view from the bridge at Batu 10 on the Kuching-Serian Road, which is part of the Pan Borneo Highway. He opened the bridge today. (Bernama pic)KUCHING: The Pan Borneo Highway project is 82% complete, and the full projected, including the Trans Borneo Highway from Sarawak to Sabah, is expected to be ready in five years, works minister Fadillah Yusof said.
He said work has been completed on four packages: Telok Melano-Sematan, Nyabau, Serian-Balai Ringin and Julau.
“The remaining packages, hopefully, will be completed by the end of this year. One or two packages could be delayed due to the challenges, especially the shortage of building materials and their rising costs,” Fadillah said.
“Meanwhile, many foreign workers have not come in, specifically from Indonesia as Sarawak only accepts those from that neighbouring country.
“The increase in the price of diesel is also another challenge faced by the contractors, besides the cost of steel,” he said.
The Sarawak public works department and the federal works ministry were working closely to complete phase one by the year-end with a bit carried forward to next year,” he said.
He was speaking after opening the Batu 10 bridge on the Kuching-Serian Road, which is part of the Pan Borneo Highway.
Fadillah said phase one of the Sabah-Sarawak Link Road, which is part of the Trans Borneo Highway, was being implemented. The highway will connect the divisions in Sarawak.
“Our target in the next five years is to complete the remaining part of the Pan Borneo phase two and the Trans Borneo Sarawak, covering the Brunei by-pass.
“Hence, Limbang and Lawas residents will be able to travel to Miri and then via the land routes to the other divisions,” he added.
Phase one of the Pan Borneo Sarawak Highway project worth RM16.117 billion involves 11 work packages with a 786-kilometre route from Telok Melano in Miri while the Pan Borneo Highway phase two from Limbang to Lawas is expected to be ready by 2028. - FMT


Artikel ini hanyalah simpanan cache dari url asal penulis yang berkebarangkalian sudah terlalu lama atau sudah dibuang :

http://malaysiansmustknowthetruth.blogspot.com/2022/05/pan-borneo-highway-is-82-complete-says.html

Kempen Promosi dan Iklan
Kami memerlukan jasa baik anda untuk menyokong kempen pengiklanan dalam website kami. Serba sedikit anda telah membantu kami untuk mengekalkan servis percuma aggregating ini kepada semua.

Anda juga boleh memberikan sumbangan anda kepada kami dengan menghubungi kami di sini
Proposals For New Highways In Klang Valley Approved Says Works Minister

Proposals For New Highways In Klang Valley Approved Says Works Minister

papar berkaitan - pada 24/5/2022 - jumlah : 209 hits
Fadillah Yusof says even with the new highways there is no guarantee congestion will reduce given the increase in the number of vehicles on the road KUALA LUMPUR The government has approved proposals from the private sector for the construc...
Sarawak Can T Speed Up Citizenship For Stateless Children Says Minister

Sarawak Can T Speed Up Citizenship For Stateless Children Says Minister

papar berkaitan - pada 19/5/2022 - jumlah : 133 hits
Sarawak minister Fatimah Abdullah says the issue of citizenship for groups such as stateless children is a federal matter KUCHING The Sarawak government cannot determine the pace to process applications for citizenship of stateless children...
Airasia Says Sorry For Flight Disruptions

Airasia Says Sorry For Flight Disruptions

papar berkaitan - pada 11/5/2022 - jumlah : 408 hits
AirAsia Malaysia says it is now operating with only 40 planes compared to almost 100 before the pandemic KUALA LUMPUR AirAsia says it has taken note of the recent flight disruptions and apologised to customers for the inconvenience caused d...
Final Decision To Extend Visa Contract Lies With Home Minister Not Pm Says Witness

Final Decision To Extend Visa Contract Lies With Home Minister Not Pm Says Witness

papar berkaitan - pada 18/5/2022 - jumlah : 200 hits
Former home minister Ahmad Zahid Hamidi is facing multiple charges of receiving bribes from a company to extend its contract as the operator of the foreign visa system in China SHAH ALAM The High Court was today told that the minutes of for...
Rm1 3b Project Will Resolve Kelantan Water Woes Says Minister

Rm1 3b Project Will Resolve Kelantan Water Woes Says Minister

papar berkaitan - pada 13/5/2022 - jumlah : 130 hits
Tuan Ibrahim Tuan Man says the project will help to mitigate the flood problem in the state KOTA BHARU Environment and water minister Tuan Ibrahim Tuan Man says the construction of a water reservoir known as the Takungan Air Pinggiran Sunga...
Disclose Studies That Led To New Highway Approvals Says Rep

Disclose Studies That Led To New Highway Approvals Says Rep

papar berkaitan - pada 27/5/2022 - jumlah : 113 hits
Rajiv Rishyakaran says there has been no disclosures on justifications traffic environmental and social impact studies PETALING JAYA The federal government should disclose the studies that led to the approval of three new highways including...
Stop Blaming Crew Members For Flight Delays Says Union

Stop Blaming Crew Members For Flight Delays Says Union

papar berkaitan - pada 18/5/2022 - jumlah : 155 hits
Videos of passengers expressing anger at airline crew members over flight delays have gone viral on social media lately PETALING JAYA The National Union of Flight Attendants Malaysia has urged passengers to stop pointing fingers at airline ...
Tajuddin S Appointment A Disaster Says Ex Diplomat

Tajuddin S Appointment A Disaster Says Ex Diplomat

papar berkaitan - pada 18/5/2022 - jumlah : 175 hits
G25 s Noor Farida Mohd Ariffin says Tajuddin Abdul Rahman s handling of the collision involving two LRT trains last year is a reflection of the Pasir Salak MP s intelligence PETALING JAYA A former diplomat has described Tajuddin Abdul Rahma...
Pkr Polls Must Go On Says Election Chief After Complaints

Pkr Polls Must Go On Says Election Chief After Complaints

papar berkaitan - pada 17/5/2022 - jumlah : 146 hits
PKR members are voting in a hybrid election casting physical ballots at voting centres or through the party s ADIL app PETALING JAYA The PKR election committee has defended the electoral process for the party elections currently being held ...
Nak Rasa Cromboloni Sedap Boleh Ke Flour Crown Jitra

Aku Ceraikan Isteri Ikut Kehendak Dia Sebab Dia Tak Pandai Buat Air Ikut Tekak Keturunan Kami

Buah Ciku 10 Khasiat Pelbagai Jenis Penyakit

Stop The Drip Stay Warm A Guide To Oil Tank Replacement Services

Kempen Pn Dijangka Menggila Selepas Usaha Serang Kerajaan Tak Berhasil

Harga Kesihatan Memastikan Suplemen Makanan Dilindungi Di Malaysia

Kelantan Kereta Rumah Ditembak Suspek Diburu Polis

Don T Wait For A Leak Proactive Planning For Oil Tank Replacement



5 Negara Yang Memilih Untuk Tidak Menggunakan Matawang Sendiri

Info Dan Sinopsis Drama Berepisod Aku Bukan Ustazah Slot Akasia TV3

Info Dan Sinopsis Drama Berepisod Bercakap Dengan Jun Slot DramaVaganza Astro Ria

5 Amalan Muslim Yang Sering Dijadikan Bahan Lawak di Malaysia

6 Fungsi Kereta Yang Sepatutnya Ada Tapi Tak Dijadikan Standard


Warna Hitam Tetap Menarik Dan Cantik Dipakai Dipagi Hari Raya

Perasaan Bila Orang Namakan Kucing Mereka Dgn Nama Anda

How To Choose A Patent Lawyer In New York For Your Invention

Ai Text Humanizer Bridging The Gap Between Ai And Human Writing

Pas Anggap Terlalu Awal Bincang Pertukaran Mb Perlis

Khaled Loyal Umno Voter Base Is Shrinking