Lrt3 Scheduled To Begin Operating On Sept 30


The overall progress of the LRT3 project, which spans from Bandar Utama to Johan Setia, has reached 98.16%. (Bernama pic)
KUALA LUMPUR: The light rail transit line 3 (LRT3) in the Klang Valley is scheduled to begin operations on Sept 30, after the project’s handover to Prasarana Malaysia Bhd by the turnkey contractor on July 31.

The transport ministry, in a written parliamentary reply yesterday, said the overall progress of the project, which spans from Bandar Utama to Johan Setia, had reached 98.16%.
It said that train operation tests without passengers would be conducted in two stages to ensure the safety of the LRT3 service for users.
“These two tests cover compliance, durability, and the safety of the rail system as well as SOPs. They involve a trial run that will be conducted concurrently with the fault free run test by the project’s main contractor, Setia Utama LRT3 Sdn Bhd,” it said.
Testing is expected to take 75 days, with the results of the fault free run test evaluated by the Land Public Transport Agency (Apad) in terms of safety, standard compliance, and specific rail system guarantees.
The ministry was responding to Azli Yusof (PH-Shah Alam), who asked for clarification on the current status of the LRT3 project, the duration of the trial run without passengers, and whether it was on target for full operation by the third quarter of 2025.
The ministry said the trial run and fault free run test are expected to begin in mid-April and finish by the end of June.
Once they are completed and approved by Apad, a trial operation will be conducted by Rapid Rail Sdn Bhd as the licensed rail operator, with technical support from the main contractor.
“The estimated duration of the trial operation test is 60 days. The trial operation test is expected to begin in July and conclude by the end of August,” the transport ministry said. - FMT


Artikel ini hanyalah simpanan cache dari url asal penulis yang berkebarangkalian sudah terlalu lama atau sudah dibuang :

http://malaysiansmustknowthetruth.blogspot.com/2025/02/a_782.html

Kempen Promosi dan Iklan
Kami memerlukan jasa baik anda untuk menyokong kempen pengiklanan dalam website kami. Serba sedikit anda telah membantu kami untuk mengekalkan servis percuma aggregating ini kepada semua.

Anda juga boleh memberikan sumbangan anda kepada kami dengan menghubungi kami di sini
Lrt3 To Begin Operations On Sept 30 Ministry

Lrt3 To Begin Operations On Sept 30 Ministry

papar berkaitan - pada 27/2/2025 - jumlah : 146 hits
The Light Rail Transit Line 3 in the Klang Valley is scheduled to start operations on Sept 30 2025 after the project s handover to Prasarana Malaysia Bhd by the turnkey contractor on July 31 The Transport Ministry in a written response post...
Anwar Arrives In Hanoi To Begin Two Day Working Visit To Vietnam

Anwar Arrives In Hanoi To Begin Two Day Working Visit To Vietnam

papar berkaitan - pada 26/2/2025 - jumlah : 149 hits
HANOI Prime Minister Datuk Seri Anwar Ibrahim arrived here for a two day working visit to Vietnam during which he is scheduled to deliver a keynote address at the 2nd Asean Future Forum on Wednesday The special aircraft carrying the Prime M...
Muslims In Indonesia To Begin Fasting Tomorrow

Muslims In Indonesia To Begin Fasting Tomorrow

papar berkaitan - pada 1/3/2025 - jumlah : 828 hits
Indonesian officials in Jakarta with a digital theodolite for the sighting of the Ramadan crescent this evening JAKARTA Muslims in Indonesia will begin fasting on Saturday while those in Singapore Thailand and Cambodia will commence fasting...
Mrcb Wins Rm2 47bil Lrt3 Contract

Mrcb Wins Rm2 47bil Lrt3 Contract

papar berkaitan - pada 28/2/2025 - jumlah : 111 hits
MRCB said SULRT3 s experience as the LRT3 main contractor meant that it was well placed to mitigate construction risks such as fluctuations in the price of materials PETALING JAYA A Malaysian Resources Corporation Berhad subsidiary has been...
Lrt3 Tarikh Operasi Senarai Stesen Fakta Menarik

Lrt3 Tarikh Operasi Senarai Stesen Fakta Menarik

papar berkaitan - pada 27/2/2025 - jumlah : 220 hits
Transit Aliran Ringan 3 merupakan projek pengangkutan awam yang dinanti nantikan menghubungkan Bandar Utama di Petaling Jaya dengan Johan Setia di Klang Projek ini bertujuan untuk mengurangkan kesesakan lalu lintas dan meningkatkan mobiliti...
Ai Tools For Monitoring Terrorist Threats

Mortgage Your House Understanding The Meaning And Implications

Terima Kasih Pak Lah Perdana Menteri Malaysia Ke 5 Bapa Pembangunan Modal Insan Negara

Iconic Photo Of Pak Lah Mother Worth A Million Votes

Kitchen Design Creating A Functional And Beautiful Space

Maruah Negara Diperleceh Isu Bendera Malaysia Maszlee Gesa Tindakan Tegas

User Acquisition And Retention

Navigating The Legal Landscape Lawyers In Washington D C


echo '';
Info Dan Sinopsis Drama Berepisod Dendam Seorang Madu Slot Tiara Astro Prima

10 Fakta Biodata Amira Othman Yang Digosip Dengan Fattah Amin Penyanyi Lagu Bila Nak Kahwin

5 Tips Macam Mana Nak Ajak Orang Kita Suka Dating Dengan Kita

Info Dan Sinopsis Drama Berepisod Keluarga Itu Slot Lestary TV3

Bolehkah Manusia Transgender Mencapai Klimaks Selepas Bertukar


Indahnya Syawal Pantun Hari Raya Menyemarakkan Suasana Aidilfitri

Dividen Bank Rakyat 2024 17

Salam Aidil Fitri Buat Pembaca Blog Cik Matahariku

Level Up Your Style The Coolest Geek Nerd Shirts At Geeksoutfit

Parcel Akak Suria Amanda Pak Zain

Video Chinese Journalists Commended For Speaking Fluent Malay While Enjoying Nasi Kandar